Kanata Lakes Golf Course Proposed Redevelopment
The owners of the former 70-hectare Kanata Lakes Golf and Country Club in Kanata North are proposing to redevelop the site into a residential community.
ClubLink Corporation submitted Plan of Subdivision (D07-16-19-0026) and Zoning By-law Amendment (D02-02-19-0123) applications to the City on October 8, 2019 to permit the development of a subdivision consisting of a variety of residential land-uses (R1, R2, R3 and R5 zones) with approximately 1500 residential units in total (Application Details - Development Applications Search). The project proposes a mix of detached dwellings, townhouse dwellings, back-to-back townhouses, stacked townhouses, apartment blocks, parks, open space, stormwater ponds, and associated infrastructure.
Proposed Development:
Map prepared by NAK Design StrategiesThe subdivision design according to the proponent's application for the project includes 70 hectares of total site area, with 33 hectares dedicated to residential land, 14 hectares dedicated to roads, and 23 hectares planned to be dedicated as parks, open space, landscape buffers and stormwater management ponds.
Ultimately, these applications were appealed by ClubLink to the Ontario Land Tribunal for a lack of decision within statutory timeframes in March 2020.
Legal Context
The City of Ottawa opposed redevelopment of the former golf course lands before the Ontario Land Tribunal. The appeal involved land-use considerations and the legal agreement dating back to 1981 (later updated in 1988) which required that 40 per cent of the total development area be designated as open space for the community, including the golf course lands. The Ontario Land Tribunal ultimately decided in favour of the appellant (ClubLink) and on January 27, 2026 issued both a zoning by-law amendment and draft plan of subdivision approval under the Planning Act. The City’s leave to appeal was also rejected by The Supreme Court of Canada. Timelines listed below:
May 1981 and updated in 1988 – Legal agreement requiring 40 per cent of the total development area of the community be open space, including the golf course lands, between the City of Kanata and Campeau Corp.
October 2019 – ClubLink Corporation submitted Plan of Subdivision (D07-16-19-0026) and Zoning By-law Amendment (D02-02-19-0123) applications to the City
March 2020 – ClubLinks Plan of Subdivision and Zoning By-law Amendment were appealed to the Local Planning Appeal Tribunal
July 2020 – The impact of the Forty Percent Agreement on the subject lands was subject matter of a court application commenced by the City.
February 2021 – Superior Court decision in favour of the City with respect to golf course and greenspace.
November 2021 – Court of Appeal allows ClubLink's appeal with respect to provisions requiring the conveyance of the golf course if no longer used for golf course purposes and remits matter to Superior Court for consideration of the balance of agreement.
March 2022 – Ontario Land Tribunal issued an ‘in principle’ approval of the Plan of Subdivision and Zoning By-law Amendment.
August 2022 – Supreme Court of Canada denies the City’s application for leave to appeal.
October 2023 – Superior Court decision on the Forty Percent Agreement rendered in ClubLink's favour.
January 2025 – Court of Appeal decision on the Forty Percent Agreement was rendered in the applicants favour.
September 18 2025 – Supreme Court of Canada rejects City of Ottawa’s application for leave to appeal
January 27 2026 – Ontario Land Tribunal issued draft plan approval of the Plan of Subdivision and final approval of the Zoning By-law Amendment
Using this Ottawa Engage webpage
As a result of Councillor Curry’s motion, this webpage will be updated throughout the project and will serve as a central place to share project updates and provide responses to community questions.
On the right-hand side of this webpage, you can access a variety of resources:
Frequently Asked Questions (FAQ) which will be continually updated
Key documents, plans, reports provided by the proponent
Peer review or third-party reviews initiated by the City on any substantive report or work plan submitted
- Staff memos provided to Council
The reports, studies and related documentation provided in support of this project are being made available in the language submitted by the various project partners. They may be translated in whole or in part upon request. For more information, please contact KanataLakes@ottawa.ca.
To receive more updates about this project, you can subscribe to the Kanata Lakes Golf Course Proposed Redevelopment e-newsletter.
The owners of the former 70-hectare Kanata Lakes Golf and Country Club in Kanata North are proposing to redevelop the site into a residential community.
ClubLink Corporation submitted Plan of Subdivision (D07-16-19-0026) and Zoning By-law Amendment (D02-02-19-0123) applications to the City on October 8, 2019 to permit the development of a subdivision consisting of a variety of residential land-uses (R1, R2, R3 and R5 zones) with approximately 1500 residential units in total (Application Details - Development Applications Search). The project proposes a mix of detached dwellings, townhouse dwellings, back-to-back townhouses, stacked townhouses, apartment blocks, parks, open space, stormwater ponds, and associated infrastructure.
Proposed Development:
Map prepared by NAK Design StrategiesThe subdivision design according to the proponent's application for the project includes 70 hectares of total site area, with 33 hectares dedicated to residential land, 14 hectares dedicated to roads, and 23 hectares planned to be dedicated as parks, open space, landscape buffers and stormwater management ponds.
Ultimately, these applications were appealed by ClubLink to the Ontario Land Tribunal for a lack of decision within statutory timeframes in March 2020.
Legal Context
The City of Ottawa opposed redevelopment of the former golf course lands before the Ontario Land Tribunal. The appeal involved land-use considerations and the legal agreement dating back to 1981 (later updated in 1988) which required that 40 per cent of the total development area be designated as open space for the community, including the golf course lands. The Ontario Land Tribunal ultimately decided in favour of the appellant (ClubLink) and on January 27, 2026 issued both a zoning by-law amendment and draft plan of subdivision approval under the Planning Act. The City’s leave to appeal was also rejected by The Supreme Court of Canada. Timelines listed below:
May 1981 and updated in 1988 – Legal agreement requiring 40 per cent of the total development area of the community be open space, including the golf course lands, between the City of Kanata and Campeau Corp.
October 2019 – ClubLink Corporation submitted Plan of Subdivision (D07-16-19-0026) and Zoning By-law Amendment (D02-02-19-0123) applications to the City
March 2020 – ClubLinks Plan of Subdivision and Zoning By-law Amendment were appealed to the Local Planning Appeal Tribunal
July 2020 – The impact of the Forty Percent Agreement on the subject lands was subject matter of a court application commenced by the City.
February 2021 – Superior Court decision in favour of the City with respect to golf course and greenspace.
November 2021 – Court of Appeal allows ClubLink's appeal with respect to provisions requiring the conveyance of the golf course if no longer used for golf course purposes and remits matter to Superior Court for consideration of the balance of agreement.
March 2022 – Ontario Land Tribunal issued an ‘in principle’ approval of the Plan of Subdivision and Zoning By-law Amendment.
August 2022 – Supreme Court of Canada denies the City’s application for leave to appeal.
October 2023 – Superior Court decision on the Forty Percent Agreement rendered in ClubLink's favour.
January 2025 – Court of Appeal decision on the Forty Percent Agreement was rendered in the applicants favour.
September 18 2025 – Supreme Court of Canada rejects City of Ottawa’s application for leave to appeal
January 27 2026 – Ontario Land Tribunal issued draft plan approval of the Plan of Subdivision and final approval of the Zoning By-law Amendment
Using this Ottawa Engage webpage
As a result of Councillor Curry’s motion, this webpage will be updated throughout the project and will serve as a central place to share project updates and provide responses to community questions.
On the right-hand side of this webpage, you can access a variety of resources:
Frequently Asked Questions (FAQ) which will be continually updated
Key documents, plans, reports provided by the proponent
Peer review or third-party reviews initiated by the City on any substantive report or work plan submitted
- Staff memos provided to Council
The reports, studies and related documentation provided in support of this project are being made available in the language submitted by the various project partners. They may be translated in whole or in part upon request. For more information, please contact KanataLakes@ottawa.ca.
To receive more updates about this project, you can subscribe to the Kanata Lakes Golf Course Proposed Redevelopment e-newsletter.
-
Environmental Assessment and Peer Review Update – April 28, 2026
Share Environmental Assessment and Peer Review Update – April 28, 2026 on Facebook Share Environmental Assessment and Peer Review Update – April 28, 2026 on Twitter Share Environmental Assessment and Peer Review Update – April 28, 2026 on Linkedin Email Environmental Assessment and Peer Review Update – April 28, 2026 link
Environmental Conditions in Draft Approval
There are four conditions in the draft plan of subdivision approval the proponent received from the Ontario Land Tribunal which outline the environmental requirements that the proponent must satisfy prior to the redevelopment of the site:
- A Record of Site Condition (RSC) under Ontario Regulation 153/04 which has been acknowledged by the MECP and confirms that the site is suitable for the proposed residential use;
- A remedial action plan to address soil contamination at the site;
- An updated Phase Two Environmental Site Assessment (ESA) with a remediation report appended that documents the remedial work completed at the site; and,
- A plan outlining control and mitigation measures for dust, odour, noise and sediment during all phases of excavation work.
The RSC requirement will ensure that the environmental site assessment and remediation work is conducted in accordance Ontario Regulation 153/04, to be overseen by a Qualified Person defined under the regulation and reviewed/approved by MECP’s technical staff.
Previous Environmental Site Assessments
The City of Ottawa has received two Phase One ESAs (dated 2018 and 2021) and three Phase Two ESAs (dated 2019, 2020 and 2021) completed by Paterson Group as part of the previous development applications for the site.
The 2021 Phase One ESA indicates that the site was historically vacant land, possibly used for agricultural purposes, prior to the development of the original 9-hole golf course in the late 1960s. Nine additional holes were added between 1976 and 1990. The Phase One ESA identified the aboveground fuel storage tanks and the storage and application of pesticides and herbicides as the two areas of potential environmental concern (APEC) at the site. No concerns regarding the surrounding properties were identified.
The most recent Phase Two ESA dated 2021 summarizes the various phases of field work completed at the site in 2019 and 2020. The 2019 investigation included advancement of 20 boreholes across the site, of which 13 were developed as monitoring wells, along with completion of 20 shallow hand auger holes. In 2020, an additional 34 shallow hand auger holes were advanced across the site in May 2020 and 24 further shallow hand auger holes completed in December 2020. Soil and groundwater samples collected as part of the ESAs were selectively analyzed for contaminants of concern depending on the area being investigated, and included benzene, toluene, ethylbenzene, and xylenes (BTEX), petroleum hydrocarbon fractions (PHCs), metals and/or pesticides.
The 2021 Phase Two ESA identified mercury in shallow soil samples across the site in excess of the applicable Ontario Ministry of Environment, Conservation and Parks (MECP) standard. The mercury is attributed to historical use of mercury-containing fungicides at the golf course which were used to control snow mold growth during the winter months. Although these fungicides were typically applied to putting greens, studies have indicated that elevated levels of mercury could extend up to 15 m from the putting surfaces where applied, or be present in other areas such as tee boxes or storage/maintenance yards. These types of mercury containing fungicides were generally discontinued from use in the 1990s.
In total, 74 soil samples collected across the site were analyzed for mercury as part of these initial studies and 15 samples, or approximately 20 per cent, exceeded the MECP standard for mercury. The maximum concentration of mercury measured at the site as part of the initial studies was 2.7 ug/g. Exceedances were not evenly distributed in soil across the golf course. The highest frequencies were observed in samples collected from the putting greens, where 69% of the 16 samples exceeded the standard, and at tee box areas where 50% of the 4 samples reported exceedances. In contrast, soil samples collected in the roughs, fairways, and other areas across the golf course had low or no exceedances. Most elevated results occurred in shallow soils (0–15 cm) with deeper samples showing no exceedances. Based on information provided to the City, the data indicates that not all greens have been investigated, and limited sampling has been completed at the tee boxes.
WSP’s Role as Independent Technical Advisor to the City
Given the significant public interest associated with the former Kanata Lakes golf course, the City has retained WSP Canada Inc. to provide independent technical advice beyond the City’s typical role in development review. WSP’s role is to:
- Review environmental submissions associated with specific Draft Plan Approval conditions;
- Assess whether proposed investigations, mitigation measures, and conclusions are consistent with recognized professional standards and industry best practices; and,
- Identify potential gaps, uncertainties, or risks that City staff may wish the proponent to address.
The third party review being undertaken WSP is not required under the draft approval conditions, but rather represents an additional commitment by the City to address community concerns. WSP’s peer reviews inform City staff’s oversight and help determine whether additional clarification or information should be requested from the proponent. WSP does not replace the proponent’s Qualified Person, does not direct on‑site work, and does not approve environmental investigations or provide regulatory sign‑off. The enhanced oversight approach, including the engagement of WSP, reflects the size and complexity of the site, the level of public interest, and the City’s desire to independently validate that development‑related environmental conditions are being addressed in a transparent and technically sound manner.
WSP Peer Review of 2021 Phase One/Two ESAs
The Paterson 2021 Phase One and Phase Two ESAs were peer-reviewed by WSP Canada Inc. in March 2026. The peer review was provided to the proponent for response and has also been posted to the Engage Ottawa page. WSP’s review of the previous environmental reports found numerous deficiencies which can be broadly grouped into the following categories:
1. Regulatory Compliance & Conformance to O. Reg. 153/04
The Phase One and Two ESA reports do not consistently conform to Ontario Regulation 153/04 requirements. Key issues include incorrect ESA terminology, incomplete adherence to the reporting requirements, missing mandatory elements (e.g., plan of survey, compliant figures), and report aging concerns. Updates will be required to support future filing of multiple Records of Site Condition (RSCs).
2. Site History & Study Area Definition
The Phase One ESA relies too heavily on distance‑based criteria to define the Study Area and excludes relevant lines of evidence. Historical land use documentation contains inaccuracies and omissions, including failure to recognize certain off‑site potentially contaminating activities (e.g., transformer station). Errors in land use tables reduce confidence in the identification of Areas of Potential Environmental Concern (APECs).
3. Natural Environment & Environmental Sensitivity
The assessment of Areas of Natural Significance is incomplete. Available provincial data indicate potential presence of threatened or endangered species, which may classify the Site as environmentally sensitive under O. Reg. 153/04. This has direct implications for the selection of applicable Site Condition Standards and Phase Two investigation requirements.
4. Physical Setting & Hydrogeological Understanding
Descriptions of geology, soils, groundwater, and well records are inconsistent or insufficiently substantiated. Soil pH and grain size data are inadequate to support selection of appropriate Site Condition Standards across the Site and future parcels.
5. Contaminants, PCAs & Conceptual Site Models
Conceptual Site Models are incomplete and internally inconsistent. Certain potentially contaminating activities (PCAs) and contaminants of potential concern (COPC) are not fully characterized, including fuel-related contaminants from aboveground storage tanks and historical herbicide use. Imported and reworked fill, sand traps, and relocated course features are not consistently addressed as potential APECs.
6. Mercury‑Specific Impacts
Mercury exceeds applicable Site Condition Standards at multiple shallow soil locations. The reports do not adequately recognize historical use of mercurial fungicides as a primary APEC, nor do they delineate the full lateral and vertical extent of mercury impacts. No methyl‑mercury analyses were completed, and consideration of historic green relocations and runoff pathways to the on-site water features is limited.
7. Sampling Design & Data Gaps
Sampling density and scope are insufficient in several areas, including soil pH, sediment within on‑site ponds, and characterization of reworked or imported materials. Contaminant migration pathways are not fully assessed, limiting confidence in overall site characterization and suitability for RSC filing.
8. QA/QC & Data Reliability
The number of field duplicate samples does not meet regulatory minimums, and quality assurance and quality control (QA/QC) sampling was not completed for all contaminants of potential concern. Some reported QA/QC metrics (e.g., relative percent differences or RPDs) are unclear or internally inconsistent, requiring additional sampling or clarification.
9. Figures, Tables & Reporting Quality
Figures and tables do not meet regulatory requirements and contain location errors, missing parameters, and insufficient labeling. Crosssections and contaminant distribution figures are limited, particularly given the need for multiple RSCs. Several internal inconsistencies and incomplete report sections were also identified.
While these concerns must be addressed prior to filing the RSCs with the MECP and prior to the City granting development approvals, they are not sufficient to immediately suspend engineering activities at the site. Based on the nature of the work occurring to date — namely, testing and investigation to address conditions of the draft subdivision approval the proponent received from the Ontario Land Tribunal — there is no violation of the Site Alteration By-law. As such, the City does not have the legal authority to issue a stop‑work order under the Act.
To satisfy the subdivision draft approval conditions and be compliant with provincial regulations, both ESA reports will require revision and supplementary Phase Two work. Key needs include additional sampling (mercury speciation, sediment, soil pH, QA/QC), refinement of conceptual site models, and improved documentation to support multiple RSC submissions. Updated Phase One and Two ESAs will be required by the proponent to obtain the Record of Site Condition(s) from the Ontario MECP which are necessary for the site redevelopment and a condition of the draft subdivision approval. The proponent is also required by the draft approval to submit their remediation plan to the City – determining the adequacy of this submission will be contingent on having an updated Phase Two ESA report outlining all of the soil and groundwater sampling data across the site. This will be another checkpoint at which the City and WSP will provide technical comments to the proponent on the adequacy of environmental site assessment work.
Proponent Response to WSP Peer Review
The environmental consultant retained by the proponent, Paterson Group, has prepared a response to the WSP peer review dated April 2, 2026. The Paterson memo acknowledges all of the WSP technical comments and confirms that the Phase One and Two ESA reports will be formally updated to fully meet Ontario Regulation 153/04 requirements before future Records of Site Condition (RSCs) are filed. The memo acknowledges that additional soil sampling and delineation (including analysis for methylmercury) will be required, and that report figures, mapping, and documentation will be enhanced to more clearly show sampling locations and site conditions. The following key items will be tracked by WSP and the City as the development application progresses:
- Deferral to Future RSC Filing – Although Paterson agrees with almost all technical comments, all substantive issues will be deferred to the future RSC filing. Until the future RSC filling is accepted by MECP, the current ESAs continue to remain inadequate for development approval.
- Environmental Sensitivity / Species at Risk - Paterson states they are investigating the possibility of Species at Risk within 30 m of future RSC parcels. The City will request to review the information and analysis collected by the proponent for this determination.
- Sediment vs. Soil Interpretation - Paterson technically agrees to sampling the water ponds at the site and reframes sediments as “soil” under O. Reg. 153/04 definitions, as they do not consider the ponds on the site to be “water bodies” as defined by the regulation (i.e., a permanent stream, river or similar watercourse or a pond or lake, but does not include a pond constructed on the property for the purpose of controlling surface water drainage). The underlying assumptions will be examined in detail upon receipt and assessment of additional study findings.
WSP is currently reviewing Paterson’s response and will advise the City if future discussions are warranted at this time. Overall, it is expected that additional soil sampling will be required to address data gaps as the developer works towards obtaining a Record of Site Condition for the redevelopment in accordance with the provincial legislation.
Submissions Related to Dust/Sediment Control
Condition 93 of the draft approval requires the developer to implement dust, sediment, noise and odour mitigation control measures during all phases of excavation work due to the presence of mercury contamination in the soils on-site. The following documents and correspondence related to these submissions are summarized below:
- The proponent’s consultant, Paterson Group, provided the City with a memo (dated February 13, 2026) outlining the proposed dust and sediment controls to be implemented during the preliminary engineering works which included: separation of proposed works from areas with known mercury exceedances; installation of silt fencing and sediment traps; use of mats at controlled exit points to prevent soil tracking onto roadways; and further testing of excavated soils in preliminary work areas with removal of any soil that exceeds provincial soil standards.
- WSP Canada Inc. completed a peer review of the Paterson memo (dated February 23, 2026) on behalf of the City and indicated that the proposed controls appeared reasonable given the known site conditions, however they recommended that documentation be prepared outlining how mitigation measures would be implemented and monitored, along with contingency measures in the event of a failure of any control measure. WSP also recommended development of a complaint tracking and response procedure, and a soil management plan.
- Paterson provided a response to WSP’s review (dated March 11, 2026), including submission of a Soil Management Plan (dated March 13, 2026) outlining how excess soil would be managed in accordance with Ontario Regulation 406/19, and the Environmental Protection Plan prepared by the contractor (Thomas Cavanagh Construction Ltd.) retained to complete the preliminary engineering works.
- WSP reviewed these additional submissions and provided some further comments to the proponent. Paterson provided two additional documents in response to the WSP comments, including a memorandum acknowledging the WSP comments (dated April 1, 2026), and an updated Soil Management Plan (dated April 1, 2026) with a revised figure showing the work areas. The Paterson response confirmed that the measures used to control soil tracking onto surrounding streets was working as intended, and that previous references to work on other parcels of the golf course had been removed, as the scope of the current works was revised to only Parcel 1.
The proponent has indicated in their most recent project update that the preliminary engineering works have been completed. All erosion and sediment control measures—including silt fencing and straw bales—will remain in place to ensure ongoing environmental protection. Regular site visits will be completed by the proponent to monitor stormwater flowing through the property and to ensure that all control measures remain effective. Any future phases of work will require a new submission outlining dust and sediment control measures to be implemented, which will be peer reviewed by WSP to ensure the proposed measures are appropriate for the site conditions, and in line with industry standards.
Recent Soil Testing Results
As part of the preliminary engineering works completed in March and April 2026, the proponent’s environmental consultant collected approximately 71 additional soil samples across the 12 work areas (pre-load pads, exfiltration manholes and bioswales). The proponent has provided the City with a preliminary summary of the soil sampling results, and indicated that mercury was detected in all but one of the 12 work areas. Overall, the measured mercury concentrations were within the range previously found at the site, and below the previous maximum mercury concentration of 2.7 micrograms per gram (µg/g). However, one area had one soil sample with a mercury concentration of 3.0 µg/g, with surrounding samples in the same area generally in the high 1.0 µg/g range.
All excavated material that exceeded the applicable site condition standards within the 12 work areas has been removed from the site to an appropriate licensed facility. The recent soil testing results will be summarized in a future Phase Two ESA report that remains a condition of the draft approval and a requirement under the Record of Site Condition.
As previously summarized in the FAQ section, the Ontario Site Condition Standards used in evaluating contamination at a site were developed by evaluating all receptors and exposure pathways that may be present at a site including who might be exposed (for example, children, adults, wildlife) and how they might be exposed (touching soil, breathing vapours, plants taking up chemicals, etc.). For each contaminant, the province has calculated several “component values” - each one representing a safe level for a particular type of exposure and receptor. The lowest of these component values then becomes the generic standard for the contaminant for that particular land use, ensuring that human health and the environment are protected.
Under the applicable standard for this site (future residential/parkland use, coarse-textured soil, no potable groundwater use), the risk pathway that drives the mercury standard is vapour intrusion from soil into the indoor air of building (“S-IA” pathway on Figure 1.1 below). That pathway would normally give a component value of 0.25 µg/g, but the background level of mercury for Table 3 sites is 0.27 µg/g which is then established as the generic standard. Exceeding 0.27 µg/g means that the MECP and the City will require that mercury‑impacted soil be remediated prior to the development of future residential homes and public parks to protect future residents in this development.
Although the maximum mercury concentration of 3.0 µg/g measured at the site to date exceeds the MECP generic standard, this maximum concentration does not exceed any other component values developed for Table 3 residential/parkland sites:
- The soil contact (S1) component value is 9.8 ug/g - this is a high-frequency, high-intensity human health exposure scenario where children and pregnant women are present and includes soil ingestion and dermal exposure.
- The ecological component values are 10 ug/g for plants and soil organisms and 20 ug/g for mammals and birds.
- The component value for soil to outdoor air (S-OA) is 36 ug/g.
- The component value for soil to groundwater to surface water (S-GW3) is 1.2E+14 ug/g – this is a soil value that is protective of aquatic life.
Overall, the mercury levels identified at this site will require remediation for the proposed residential redevelopment; but remain below levels established for most receptors and exposure pathways at the site. Although there are still some data gaps with the environmental site assessment work completed at the site, the maximum mercury concentration measured to date does not suggest that there is significant risk to surrounding residents, plants or animals. As a precaution, the City required as a condition that the developer provide a plan to control dust and sediment during all phases of work to minimize the release of mercury into the environment.

Environmental Data for City-Owned Lands
In an effort to address community concerns about the broader potential environmental impacts in the residential neighbourhood surrounding the Kanata Lakes Golf Course, the City’s Environmental Remediation Unit (ERU) conducted a review of available environmental data for City-owned property in the vicinity of the golf course. Limited soil testing was previously completed in 2023 and 2024 at two nearby parks - Weslock Park at 73 Weslock Way and Sue Nickerson Park at 88 Knudson Drive - to support excess soil management during park improvements, in accordance with Ontario Regulation 406/19. At both sites, shallow soil samples were analyzed for metals parameters, including mercury, and no exceedances were identified.
The City will be initiating more comprehensive environmental site assessments at City-owned lands in this neighbourhood in the coming months. The first phase of work will include completion of Phase One ESAs for 7 surrounding park sites and shallow soil sampling along 8 pathway links to the golf course. Further updates will be posted to this Engage Ottawa webpage as the work progresses.
The following map shows the location of the seven City-owned parks adjacent to the Kanata Lakes Golf Course where Phase One ESAs will be initiated by the City this year (labelled A through G). The Phase One ESA is the first step in the environmental site assessment process, and involves a review of the current and historical activities on the site and surrounding properties (generally within a 250 metre radius of the site) to determine if there are potential and/or actual areas of environmental concern on the site. The Phase One ESA includes a review of regulatory and historical records, interviews with personnel knowledgeable about the site history and/or operations, along with completion of a site inspection. Phase Two ESAs will then be prioritized and completed on these City parks based on the findings and recommendations from the Phase One ESAs.
The City of Ottawa also owns eight smaller parcels of land that provide pathway connections to the golf course (shown as red dots on the map). Due to their small size, Phase One ESAs will not be completed on these parcels, but instead shallow soil samples will be collected to investigate whether there may be a broader concern with mercury impacts beyond the limits of the golf course property.


Environmental Conditions in Draft Approval
There are four conditions in the draft plan of subdivision approval the proponent received from the Ontario Land Tribunal which outline the environmental requirements that the proponent must satisfy prior to the redevelopment of the site:
- A Record of Site Condition (RSC) under Ontario Regulation 153/04 which has been acknowledged by the MECP and confirms that the site is suitable for the proposed residential use;
- A remedial action plan to address soil contamination at the site;
- An updated Phase Two Environmental Site Assessment (ESA) with a remediation report appended that documents the remedial work completed at the site; and,
- A plan outlining control and mitigation measures for dust, odour, noise and sediment during all phases of excavation work.
The RSC requirement will ensure that the environmental site assessment and remediation work is conducted in accordance Ontario Regulation 153/04, to be overseen by a Qualified Person defined under the regulation and reviewed/approved by MECP’s technical staff.
Previous Environmental Site Assessments
The City of Ottawa has received two Phase One ESAs (dated 2018 and 2021) and three Phase Two ESAs (dated 2019, 2020 and 2021) completed by Paterson Group as part of the previous development applications for the site.
The 2021 Phase One ESA indicates that the site was historically vacant land, possibly used for agricultural purposes, prior to the development of the original 9-hole golf course in the late 1960s. Nine additional holes were added between 1976 and 1990. The Phase One ESA identified the aboveground fuel storage tanks and the storage and application of pesticides and herbicides as the two areas of potential environmental concern (APEC) at the site. No concerns regarding the surrounding properties were identified.
The most recent Phase Two ESA dated 2021 summarizes the various phases of field work completed at the site in 2019 and 2020. The 2019 investigation included advancement of 20 boreholes across the site, of which 13 were developed as monitoring wells, along with completion of 20 shallow hand auger holes. In 2020, an additional 34 shallow hand auger holes were advanced across the site in May 2020 and 24 further shallow hand auger holes completed in December 2020. Soil and groundwater samples collected as part of the ESAs were selectively analyzed for contaminants of concern depending on the area being investigated, and included benzene, toluene, ethylbenzene, and xylenes (BTEX), petroleum hydrocarbon fractions (PHCs), metals and/or pesticides.
The 2021 Phase Two ESA identified mercury in shallow soil samples across the site in excess of the applicable Ontario Ministry of Environment, Conservation and Parks (MECP) standard. The mercury is attributed to historical use of mercury-containing fungicides at the golf course which were used to control snow mold growth during the winter months. Although these fungicides were typically applied to putting greens, studies have indicated that elevated levels of mercury could extend up to 15 m from the putting surfaces where applied, or be present in other areas such as tee boxes or storage/maintenance yards. These types of mercury containing fungicides were generally discontinued from use in the 1990s.
In total, 74 soil samples collected across the site were analyzed for mercury as part of these initial studies and 15 samples, or approximately 20 per cent, exceeded the MECP standard for mercury. The maximum concentration of mercury measured at the site as part of the initial studies was 2.7 ug/g. Exceedances were not evenly distributed in soil across the golf course. The highest frequencies were observed in samples collected from the putting greens, where 69% of the 16 samples exceeded the standard, and at tee box areas where 50% of the 4 samples reported exceedances. In contrast, soil samples collected in the roughs, fairways, and other areas across the golf course had low or no exceedances. Most elevated results occurred in shallow soils (0–15 cm) with deeper samples showing no exceedances. Based on information provided to the City, the data indicates that not all greens have been investigated, and limited sampling has been completed at the tee boxes.
WSP’s Role as Independent Technical Advisor to the City
Given the significant public interest associated with the former Kanata Lakes golf course, the City has retained WSP Canada Inc. to provide independent technical advice beyond the City’s typical role in development review. WSP’s role is to:
- Review environmental submissions associated with specific Draft Plan Approval conditions;
- Assess whether proposed investigations, mitigation measures, and conclusions are consistent with recognized professional standards and industry best practices; and,
- Identify potential gaps, uncertainties, or risks that City staff may wish the proponent to address.
The third party review being undertaken WSP is not required under the draft approval conditions, but rather represents an additional commitment by the City to address community concerns. WSP’s peer reviews inform City staff’s oversight and help determine whether additional clarification or information should be requested from the proponent. WSP does not replace the proponent’s Qualified Person, does not direct on‑site work, and does not approve environmental investigations or provide regulatory sign‑off. The enhanced oversight approach, including the engagement of WSP, reflects the size and complexity of the site, the level of public interest, and the City’s desire to independently validate that development‑related environmental conditions are being addressed in a transparent and technically sound manner.
WSP Peer Review of 2021 Phase One/Two ESAs
The Paterson 2021 Phase One and Phase Two ESAs were peer-reviewed by WSP Canada Inc. in March 2026. The peer review was provided to the proponent for response and has also been posted to the Engage Ottawa page. WSP’s review of the previous environmental reports found numerous deficiencies which can be broadly grouped into the following categories:
1. Regulatory Compliance & Conformance to O. Reg. 153/04
The Phase One and Two ESA reports do not consistently conform to Ontario Regulation 153/04 requirements. Key issues include incorrect ESA terminology, incomplete adherence to the reporting requirements, missing mandatory elements (e.g., plan of survey, compliant figures), and report aging concerns. Updates will be required to support future filing of multiple Records of Site Condition (RSCs).
2. Site History & Study Area Definition
The Phase One ESA relies too heavily on distance‑based criteria to define the Study Area and excludes relevant lines of evidence. Historical land use documentation contains inaccuracies and omissions, including failure to recognize certain off‑site potentially contaminating activities (e.g., transformer station). Errors in land use tables reduce confidence in the identification of Areas of Potential Environmental Concern (APECs).
3. Natural Environment & Environmental Sensitivity
The assessment of Areas of Natural Significance is incomplete. Available provincial data indicate potential presence of threatened or endangered species, which may classify the Site as environmentally sensitive under O. Reg. 153/04. This has direct implications for the selection of applicable Site Condition Standards and Phase Two investigation requirements.
4. Physical Setting & Hydrogeological Understanding
Descriptions of geology, soils, groundwater, and well records are inconsistent or insufficiently substantiated. Soil pH and grain size data are inadequate to support selection of appropriate Site Condition Standards across the Site and future parcels.
5. Contaminants, PCAs & Conceptual Site Models
Conceptual Site Models are incomplete and internally inconsistent. Certain potentially contaminating activities (PCAs) and contaminants of potential concern (COPC) are not fully characterized, including fuel-related contaminants from aboveground storage tanks and historical herbicide use. Imported and reworked fill, sand traps, and relocated course features are not consistently addressed as potential APECs.
6. Mercury‑Specific Impacts
Mercury exceeds applicable Site Condition Standards at multiple shallow soil locations. The reports do not adequately recognize historical use of mercurial fungicides as a primary APEC, nor do they delineate the full lateral and vertical extent of mercury impacts. No methyl‑mercury analyses were completed, and consideration of historic green relocations and runoff pathways to the on-site water features is limited.
7. Sampling Design & Data Gaps
Sampling density and scope are insufficient in several areas, including soil pH, sediment within on‑site ponds, and characterization of reworked or imported materials. Contaminant migration pathways are not fully assessed, limiting confidence in overall site characterization and suitability for RSC filing.
8. QA/QC & Data Reliability
The number of field duplicate samples does not meet regulatory minimums, and quality assurance and quality control (QA/QC) sampling was not completed for all contaminants of potential concern. Some reported QA/QC metrics (e.g., relative percent differences or RPDs) are unclear or internally inconsistent, requiring additional sampling or clarification.
9. Figures, Tables & Reporting Quality
Figures and tables do not meet regulatory requirements and contain location errors, missing parameters, and insufficient labeling. Crosssections and contaminant distribution figures are limited, particularly given the need for multiple RSCs. Several internal inconsistencies and incomplete report sections were also identified.
While these concerns must be addressed prior to filing the RSCs with the MECP and prior to the City granting development approvals, they are not sufficient to immediately suspend engineering activities at the site. Based on the nature of the work occurring to date — namely, testing and investigation to address conditions of the draft subdivision approval the proponent received from the Ontario Land Tribunal — there is no violation of the Site Alteration By-law. As such, the City does not have the legal authority to issue a stop‑work order under the Act.
To satisfy the subdivision draft approval conditions and be compliant with provincial regulations, both ESA reports will require revision and supplementary Phase Two work. Key needs include additional sampling (mercury speciation, sediment, soil pH, QA/QC), refinement of conceptual site models, and improved documentation to support multiple RSC submissions. Updated Phase One and Two ESAs will be required by the proponent to obtain the Record of Site Condition(s) from the Ontario MECP which are necessary for the site redevelopment and a condition of the draft subdivision approval. The proponent is also required by the draft approval to submit their remediation plan to the City – determining the adequacy of this submission will be contingent on having an updated Phase Two ESA report outlining all of the soil and groundwater sampling data across the site. This will be another checkpoint at which the City and WSP will provide technical comments to the proponent on the adequacy of environmental site assessment work.
Proponent Response to WSP Peer Review
The environmental consultant retained by the proponent, Paterson Group, has prepared a response to the WSP peer review dated April 2, 2026. The Paterson memo acknowledges all of the WSP technical comments and confirms that the Phase One and Two ESA reports will be formally updated to fully meet Ontario Regulation 153/04 requirements before future Records of Site Condition (RSCs) are filed. The memo acknowledges that additional soil sampling and delineation (including analysis for methylmercury) will be required, and that report figures, mapping, and documentation will be enhanced to more clearly show sampling locations and site conditions. The following key items will be tracked by WSP and the City as the development application progresses:
- Deferral to Future RSC Filing – Although Paterson agrees with almost all technical comments, all substantive issues will be deferred to the future RSC filing. Until the future RSC filling is accepted by MECP, the current ESAs continue to remain inadequate for development approval.
- Environmental Sensitivity / Species at Risk - Paterson states they are investigating the possibility of Species at Risk within 30 m of future RSC parcels. The City will request to review the information and analysis collected by the proponent for this determination.
- Sediment vs. Soil Interpretation - Paterson technically agrees to sampling the water ponds at the site and reframes sediments as “soil” under O. Reg. 153/04 definitions, as they do not consider the ponds on the site to be “water bodies” as defined by the regulation (i.e., a permanent stream, river or similar watercourse or a pond or lake, but does not include a pond constructed on the property for the purpose of controlling surface water drainage). The underlying assumptions will be examined in detail upon receipt and assessment of additional study findings.
WSP is currently reviewing Paterson’s response and will advise the City if future discussions are warranted at this time. Overall, it is expected that additional soil sampling will be required to address data gaps as the developer works towards obtaining a Record of Site Condition for the redevelopment in accordance with the provincial legislation.
Submissions Related to Dust/Sediment Control
Condition 93 of the draft approval requires the developer to implement dust, sediment, noise and odour mitigation control measures during all phases of excavation work due to the presence of mercury contamination in the soils on-site. The following documents and correspondence related to these submissions are summarized below:
- The proponent’s consultant, Paterson Group, provided the City with a memo (dated February 13, 2026) outlining the proposed dust and sediment controls to be implemented during the preliminary engineering works which included: separation of proposed works from areas with known mercury exceedances; installation of silt fencing and sediment traps; use of mats at controlled exit points to prevent soil tracking onto roadways; and further testing of excavated soils in preliminary work areas with removal of any soil that exceeds provincial soil standards.
- WSP Canada Inc. completed a peer review of the Paterson memo (dated February 23, 2026) on behalf of the City and indicated that the proposed controls appeared reasonable given the known site conditions, however they recommended that documentation be prepared outlining how mitigation measures would be implemented and monitored, along with contingency measures in the event of a failure of any control measure. WSP also recommended development of a complaint tracking and response procedure, and a soil management plan.
- Paterson provided a response to WSP’s review (dated March 11, 2026), including submission of a Soil Management Plan (dated March 13, 2026) outlining how excess soil would be managed in accordance with Ontario Regulation 406/19, and the Environmental Protection Plan prepared by the contractor (Thomas Cavanagh Construction Ltd.) retained to complete the preliminary engineering works.
- WSP reviewed these additional submissions and provided some further comments to the proponent. Paterson provided two additional documents in response to the WSP comments, including a memorandum acknowledging the WSP comments (dated April 1, 2026), and an updated Soil Management Plan (dated April 1, 2026) with a revised figure showing the work areas. The Paterson response confirmed that the measures used to control soil tracking onto surrounding streets was working as intended, and that previous references to work on other parcels of the golf course had been removed, as the scope of the current works was revised to only Parcel 1.
The proponent has indicated in their most recent project update that the preliminary engineering works have been completed. All erosion and sediment control measures—including silt fencing and straw bales—will remain in place to ensure ongoing environmental protection. Regular site visits will be completed by the proponent to monitor stormwater flowing through the property and to ensure that all control measures remain effective. Any future phases of work will require a new submission outlining dust and sediment control measures to be implemented, which will be peer reviewed by WSP to ensure the proposed measures are appropriate for the site conditions, and in line with industry standards.
Recent Soil Testing Results
As part of the preliminary engineering works completed in March and April 2026, the proponent’s environmental consultant collected approximately 71 additional soil samples across the 12 work areas (pre-load pads, exfiltration manholes and bioswales). The proponent has provided the City with a preliminary summary of the soil sampling results, and indicated that mercury was detected in all but one of the 12 work areas. Overall, the measured mercury concentrations were within the range previously found at the site, and below the previous maximum mercury concentration of 2.7 micrograms per gram (µg/g). However, one area had one soil sample with a mercury concentration of 3.0 µg/g, with surrounding samples in the same area generally in the high 1.0 µg/g range.
All excavated material that exceeded the applicable site condition standards within the 12 work areas has been removed from the site to an appropriate licensed facility. The recent soil testing results will be summarized in a future Phase Two ESA report that remains a condition of the draft approval and a requirement under the Record of Site Condition.
As previously summarized in the FAQ section, the Ontario Site Condition Standards used in evaluating contamination at a site were developed by evaluating all receptors and exposure pathways that may be present at a site including who might be exposed (for example, children, adults, wildlife) and how they might be exposed (touching soil, breathing vapours, plants taking up chemicals, etc.). For each contaminant, the province has calculated several “component values” - each one representing a safe level for a particular type of exposure and receptor. The lowest of these component values then becomes the generic standard for the contaminant for that particular land use, ensuring that human health and the environment are protected.
Under the applicable standard for this site (future residential/parkland use, coarse-textured soil, no potable groundwater use), the risk pathway that drives the mercury standard is vapour intrusion from soil into the indoor air of building (“S-IA” pathway on Figure 1.1 below). That pathway would normally give a component value of 0.25 µg/g, but the background level of mercury for Table 3 sites is 0.27 µg/g which is then established as the generic standard. Exceeding 0.27 µg/g means that the MECP and the City will require that mercury‑impacted soil be remediated prior to the development of future residential homes and public parks to protect future residents in this development.
Although the maximum mercury concentration of 3.0 µg/g measured at the site to date exceeds the MECP generic standard, this maximum concentration does not exceed any other component values developed for Table 3 residential/parkland sites:
- The soil contact (S1) component value is 9.8 ug/g - this is a high-frequency, high-intensity human health exposure scenario where children and pregnant women are present and includes soil ingestion and dermal exposure.
- The ecological component values are 10 ug/g for plants and soil organisms and 20 ug/g for mammals and birds.
- The component value for soil to outdoor air (S-OA) is 36 ug/g.
- The component value for soil to groundwater to surface water (S-GW3) is 1.2E+14 ug/g – this is a soil value that is protective of aquatic life.
Overall, the mercury levels identified at this site will require remediation for the proposed residential redevelopment; but remain below levels established for most receptors and exposure pathways at the site. Although there are still some data gaps with the environmental site assessment work completed at the site, the maximum mercury concentration measured to date does not suggest that there is significant risk to surrounding residents, plants or animals. As a precaution, the City required as a condition that the developer provide a plan to control dust and sediment during all phases of work to minimize the release of mercury into the environment.

Environmental Data for City-Owned Lands
In an effort to address community concerns about the broader potential environmental impacts in the residential neighbourhood surrounding the Kanata Lakes Golf Course, the City’s Environmental Remediation Unit (ERU) conducted a review of available environmental data for City-owned property in the vicinity of the golf course. Limited soil testing was previously completed in 2023 and 2024 at two nearby parks - Weslock Park at 73 Weslock Way and Sue Nickerson Park at 88 Knudson Drive - to support excess soil management during park improvements, in accordance with Ontario Regulation 406/19. At both sites, shallow soil samples were analyzed for metals parameters, including mercury, and no exceedances were identified.
The City will be initiating more comprehensive environmental site assessments at City-owned lands in this neighbourhood in the coming months. The first phase of work will include completion of Phase One ESAs for 7 surrounding park sites and shallow soil sampling along 8 pathway links to the golf course. Further updates will be posted to this Engage Ottawa webpage as the work progresses.
The following map shows the location of the seven City-owned parks adjacent to the Kanata Lakes Golf Course where Phase One ESAs will be initiated by the City this year (labelled A through G). The Phase One ESA is the first step in the environmental site assessment process, and involves a review of the current and historical activities on the site and surrounding properties (generally within a 250 metre radius of the site) to determine if there are potential and/or actual areas of environmental concern on the site. The Phase One ESA includes a review of regulatory and historical records, interviews with personnel knowledgeable about the site history and/or operations, along with completion of a site inspection. Phase Two ESAs will then be prioritized and completed on these City parks based on the findings and recommendations from the Phase One ESAs.
The City of Ottawa also owns eight smaller parcels of land that provide pathway connections to the golf course (shown as red dots on the map). Due to their small size, Phase One ESAs will not be completed on these parcels, but instead shallow soil samples will be collected to investigate whether there may be a broader concern with mercury impacts beyond the limits of the golf course property.

Language Switch
Who's Listening
-
Email KanataLakes@ottawa.ca
Stay informed through our newsletter
FAQs
-
Planning and Approval Process
- What is being proposed in the redevelopment application?
- What does draft plan of subdivision approval mean, what are the next steps in the review process, and what is the City's involvement in this process?
- How will the proposed subdivision design and construction address impacts on adjacent properties, including buffers between new and existing homes as well as grading and potential retaining walls along shared property lines?
-
The City of Ottawa's Role
- How is the City responding to the community’s concerns regarding this development?
- Can the City issue a stop‑work order?
- Has a grading or site alteration permit been issued or applied that would allow soil disturbance on the Kanata Lakes site?
- As the City holds easements on the site, can they be used to prevent this development?
- At what point does Building Code Services become involved in the review and do they review fire separation requirements?
-
On-Site Activity
- Are construction trucks allowed to be on residential streets to access the site and is the proponent responsible for repairs If the construction vehicles damage the surrounding roadways?
- How is vibration being monitored throughout ongoing site investigations?
- Why was winter ground disturbance determined to be appropriate rather than deferring work to less complicated conditions?
- How is the City protecting against tree removal on this site?
- If the proponent needs to work near the adjacent properties, what obligation do they have to notify the property owner? Many neighbours have fences or trees that may be impacted by construction work.
- Where did the proponent install the bioswales and manholes and what is their purpose?
-
Stormwater and Drainage
- What tools does the City have to ensure drainage does not have a negative impact on neighboring properties?
- Conditions on site are changing, what is the City doing to ensure adjacent properties are not impacted by flooding?
- In the event a homeowner experiences flooding, what should they be aware of in terms of insurance claims and the City’s role?
- Councillor Curry’s February 25, 2026 motion directs staff to undertake an independent drainage assessment for the former golf course lands. What work will be undertaken through this initiative and how will it assist the City?
-
Environmental and Contamination Management
- Has the entire site been evaluated for potential mercury contamination?
- How will mercury disturbance be limited while also controlling dust and sediment during the early engineering work on the site?
- How does the City monitor what enters its sewer system, and what steps are taken if contaminants such as mercury are detected?
- How will disturbance of the land and rock impact radon exposure in the area?
- Which materials and fill have been brought to the site, and how are they being managed during the construction process?
- What is the MECP standard for mercury in soil?
- What environmental conditions did the City require for this development?
- Regarding the environmental and contamination considerations on the former golf course lands, please clarify the roles and responsibilities of the Ministry of the Environment and Climate Protection (MECP), the City, and the proponent’s Qualified Person.
- Why is the City not taking action regarding community concern for the dead coyotes that were on site?
City of Ottawa Documents
-
WSP Environmental Peer Review
-
Ottawa Public Health Update - May 4 2026 (74.9 KB) (pdf)
-
7000 Campeau Drive Easement Map (751 KB) (pdf)
-
Response from Ottawa Public Health to Councilor Inquiry (54 KB) (pdf)
-
Kanata Lakes Golf Course Lands Inquiry (579 KB) (pdf)
-
Ontario Land Tribunal - January 27 2026 (4.54 MB) (pdf)
-
Ontario Land Tribunal - March 22 2022 (997 KB) (pdf)
Documents Provided by the Proponent
-
Project Updates
-
Project Update - April 24 2026 (61.8 KB) (pdf)
-
Project Update - April 17 2026 (61.2 KB) (pdf)
-
Project Update - April 10 2026 (585 KB) (pdf)
-
Project Update - April 2 2026 (611 KB) (pdf)
-
Project Update - March 27 2026 (612 KB) (pdf)
-
Project Update - March 20 2026 (614 KB) (pdf)
-
Project Update - March 12 2026 (658 KB) (pdf)
-
-
Environmental and Contamination Management
-
Proponent Response to WSP Memo for Phase 1 and Phase 2 Environmental Site Assessments - April 2 2026 (324 KB) (pdf)
-
Proponent Response to Preliminary Engineering Investigation - April 1 2026 (250 KB) (pdf)
-
Revised Soil Management Plan - April 1 2026 (1.22 MB) (pdf)
-
Soil Management Plan - March 13 2026 (422 KB) (pdf)
-
Proponent Response to WSP Technical Review - March 11 2026 (4.47 MB) (pdf)
-
Preliminary Engineering Investigations Memorandum - February 13 2026 (213 KB) (pdf)
-
Phase 2 Environmental Site Assessment - April 1 2021 (31.4 MB) (pdf)
-
Phase 1 Environmental Site Assessment - January 18 2021 (12.5 MB) (pdf)
-
-
Original Planning Application Submission from Proponent 2019 (58.9 KB) (pdf)
