Coronation Park

Share on Facebook Share on Twitter Share on Linkedin Email this link

September 29, 2023:

Work began onsite in August with utility connections (water and sewer) being made in Station Boulevard, followed by excavation of the site. Most of the inground work should be completed by the end of October. The splash pad spray elements are expected to be installed in spring 2024.


Consultation Results

Thank you to everyone who provided their input on the splash pad options for Coronation Park.

Option 1 (Vortex) was selected and construction is anticipated to commence in 2022.

Thank you again to everyone who participated!


The City is looking for your feedback on a new splash pad in Coronation Park located at 42 Coronation Avenue in Ward 18 - Alta Vista.

The concept plan and images are in the document library on the right. Take the survey below to share your feedback.

Image of Coronation Park


September 29, 2023:

Work began onsite in August with utility connections (water and sewer) being made in Station Boulevard, followed by excavation of the site. Most of the inground work should be completed by the end of October. The splash pad spray elements are expected to be installed in spring 2024.


Consultation Results

Thank you to everyone who provided their input on the splash pad options for Coronation Park.

Option 1 (Vortex) was selected and construction is anticipated to commence in 2022.

Thank you again to everyone who participated!


The City is looking for your feedback on a new splash pad in Coronation Park located at 42 Coronation Avenue in Ward 18 - Alta Vista.

The concept plan and images are in the document library on the right. Take the survey below to share your feedback.

Image of Coronation Park


Page last updated: 29 Sep 2023, 11:57 AM