The City of Ottawa's Transportation Master Plan containsa list of transportation infrastructure projects, including new sidewalks, that the City intends to construct over the coming years.This list of projects was created and prioritized based on public consultation, Councillor input and a city-wide network review. Sidewalks along Brant Street and Clarke Avenue were approved as phase 1 projects in the plan.
The provision of sidewalks in these locations aligns with the City’s transportation goals to maximize walkability and to create safe, inviting pedestrian environments for all ages and abilities.
The City of Ottawa's Transportation Master Plan containsa list of transportation infrastructure projects, including new sidewalks, that the City intends to construct over the coming years.This list of projects was created and prioritized based on public consultation, Councillor input and a city-wide network review. Sidewalks along Brant Street and Clarke Avenue were approved as phase 1 projects in the plan.
The provision of sidewalks in these locations aligns with the City’s transportation goals to maximize walkability and to create safe, inviting pedestrian environments for all ages and abilities.
Share Clark Ave and Brant St Sidewalk (Closed) on FacebookShare Clark Ave and Brant St Sidewalk (Closed) on X (formerly Twitter)Share Clark Ave and Brant St Sidewalk (Closed) on LinkedinEmail Clark Ave and Brant St Sidewalk (Closed) link
Clarke Avenue and Brant Street Sidewalks is currently at this stage
Public consultation and review of public feedback.
Summer 2026
this is an upcoming stage for Clarke Avenue and Brant Street Sidewalks
Finalize Functional Design.
After the public consultation has concluded, comments will be reviewed and the functional design will be refined. The project will then be transferred to the City’s design and construction group for the detailed design phase.
Fall 2026
this is an upcoming stage for Clarke Avenue and Brant Street Sidewalks
Initiate detailed design.
Specifics of the plan may change slightly during detailed design as the drawings are further refined.
Spring 2027
this is an upcoming stage for Clarke Avenue and Brant Street Sidewalks
Detailed/final design available for review.
Fall 2027
this is an upcoming stage for Clarke Avenue and Brant Street Sidewalks
Construction begins.
Timelines for construction are variable, and a project may be delayed to align with other project schedules.