January → March 2021

Round 1: Public & stakeholder engagement

May 20 → May 26 2021

Draft Parks and Recreation Facilities Master Plan presented to the Community and Protective Services Committee and Council

May 27 → June 17 2021

Round 2: Public & stakeholder engagement

June 18 → July 25 2021

Consultation analysis & updates to Final draft Plan

July 26 → August 24 2021

French translation of Final draft plan & accessibility; writing Consultation Summary Report

August 25 → September 22 2021

Final Parks and Recreation Facilities Master Plan presented to Planning, Community and Protective Services Committees and Council