January → March 2021

Round 1: Public & stakeholder engagement

May 20 → May 26 2021

Draft Parks and Recreation Facilities Master Plan presented to the Community and Protective Services Committee and Council

May 27 → July 30 2021

Round 2: Public & stakeholder engagement

June 18 → July 30 2021

Consultation analysis & updates to Final draft Plan

July 26 → August 25 2021

Updates to Final draft plan & accessibility; writing Consultation Summary Report

September 16 → October 13 2021

Final Parks and Recreation Facilities Master Plan presented to joint Planning & Community and Protective Services Committees and Council